This project required the initial soft strip of obsolete classroom followed by the complete demolition and removal from site of temporary class room buildings. The project carried out within the school premises was negotiated direct with the end user client with a programme requirement of start to completion within the autumn half term holidays. The project was completed, with the site cleared and our men and plant off site within 5 days.
| Duration: | 5 days |
| Client: | Oxted School |