This Roll Out project involves the complete strip out of three office buildings being fitted out in sequence with the strip out for each building to be completed within 5 weeks. The work involved mechanical and electrical strip, the removal of ceilings, partitioning and raised floors as well as the strip out of all sanitary ware. The project required an H&C team to be deployed to Coventry for the duration of the works in order that we could provide a continued service to this valued repeat business client.
| Duration: | 7 weeks |
| Client: | Overbury |